Saturday, 19 May 2018

Maintenance Update (vacuum, Edward, wagons, ash)

Wednesday 16th
With 2807 in service today and until the weekend, and then again over the gala (26th - 28th May) we are limited mainly to boot scraper production. After the gala, visiting locos get the limelight, and 2807 is stood down until 26 June.

John G volunteered to go to Winchcombe to help out on the siphon painting. The proposed freight trains over the gala weekend (26 - 28 May) have been cancelled, so our siphon is not now required.

Bruce caught up with the crew at one point and checked the situation regarding maintaining vacuum and dripping condenser (still). He now has a better idea of what needs doing. The outstanding issues are:

6: Driver side under cab side - main steam pipe to injector leaking at joint/sleeve. {Hopefully there will be time to see to this after the gala}
22: Condensing coil left hand side, first union from T-cocks towards coil is leaking. {Bruce had tightened this, but it continues to drip. Probably needs taking apart and the fault determining.}
23: Reservoir not building up to 23 inches [of vacuum] staying around 20 inches. {Possibly a leak at the vacuum cylinder gland, or the brakes need adjusting}.

On the latter, Bruce thinks that the central shaft with the vacuum piston on it is worn, and in certain positions, vacuum could be leaking by. We may get a chance next Wednesday to have a look - if we can get over a pit. Being the time that the gala visitor locos will be undergoing their steam & mechanical checks, we may not get a look in!

King Edward II

John T arrived, treating today as a pseudo-Saturday. He kindly set-to with the needle gun and cleaned seven rail chairs by end of play. Bruce had applied Deproma to four red; five green, and two black chairs. I finished off half-a-dozen boot scrapers and re-stocked the cafés.

The following photo appeared in our 1997 book, Heavyweight Champion, with the caption: “2807 hauling a demonstration train of 20 ton mineral wagons. Severn Tunnel Junction, 26.8.24.”


Ken Shuard lent me the book GWR Reflections in which the same photo appears with the caption: “.. the train is heading west and the wagons are destined for delivery to North’s Navigation Colliery, Maesteg.” The book adds more information about these wagons - where they were built and where they were intended for.

You can pick up a copy for less than £5 from the internet.


John G reports that Gil painted the siphon end doors white, and cleaned & painted the steps to the siphon doors on the North side. Fred applied brown top coat to the north side doors. John worked with Fred, and that completes all external paintwork. One double door does need replacing, but is holding for now!

Saturday 19th
Not a lot of activity on the 2807 front - only John G and I were here working. John came principally for the board meeting, but wire-brushed and angle-ground two chairs, then painted their bottoms. I moved a lot around and applied top coat to four green ones.

The crew found the cause of the loss of vacuum - a hose to the reservoir has split. It’s temporarily wrapped up in tape until Wednesday, when we will have chance to replace the hose.

2807 has set fire to sleepers recently, so we need to improve the working of the ash pan sprinkler and also fit the spark guards to the damper doors.

There is some uncertainty about when the 10-year “ticket” expires - March or May 2020. Loco Dept has asked that 2807 be kept operational until the end of ticket, and will seek an extension to end of summer season 2020, if possible. They then want us back in service, after the Heavy General Overhaul, in time for the 2024 season.


Steve

Wednesday, 9 May 2018

Maintenance Update (LNER, spring, strawberry, power)

Saturday 5th
Gorgeous day. I met Fred at Winchcombe. He said that he was here on Friday doing some painting on the siphon. The whole of the south side is now in one colour! Today he had hoped to get Gilbert to join in and paint the north side.

There was a meeting of the HGO subgroup today, at which the design of the ashpan was talked through. The hope is to begin construction of it later this year. Young Rob was at that meeting, too, having been rostered for cleaner on the first train of the day … arriving at Toddington at 05:00. So, by the end of his meeting, he was whacked, and went home.

John T and I pressed on with the usual! Bruce is into his bowls season, so misses some Saturdays. He reported back on his footplate ride last Wednesday: “I had a good trip on the footplate on Wed although it was a tad wet and cold at times, particularly when running tender first.”

I found an interesting LNER chair from July 1945. At first glance it says “Stanton”, which was a major iron & steel works up Ilkeston way. However, close examination will show that the final “N” is actually an “H”.


So, it says “STANTOH.H”. Maybe the dot-H means the Hallam Plant?

Wednesday 9th
This is the one day that 2807 is resting! So, Bruce and Gilbert tackled some of the trivia that have been reported.

The first was a (tiny) drip from a union on the condenser coil. The nut needed tightening. The reporter of this issue has a reputation for taking longer to write down and describe the issue than the time it takes to fix it.


Allegedly, when a driver went to fill up the hydrostatic lubricator, there was a ‘gurgling’ sound.


Bruce checked it over, and tightened a couple of nuts. Gil fiddled with one of the glasses that kept getting oiled up.

John finally gained access to the one tender spring that had avoided being painted.


Water was seen running down a pipe underneath the cab side. This is a known problem - there is a break in the ashpan sprinkler pipe. Water runs down a noticeably rusty pipe if the injector is on and pressure is leaking past the on/off valve. We don’t aim to fix it, so it is turned off. Bruce (or maybe it was JP?) gave the valve wheel an extra twist.



Meanwhile, John G was painting bottoms while Steve was cutting bolts, angle-grinding and wire-brushing. I played with the needle gun, and by end of play there were 11 rail chairs with black bottoms in the production line.

I had started the day with a spot of gardening, having dug up numerous bulbs from what is now my strawberry patch at home. I figured that they should make a good display in the 2807 wild flower garden next spring.

Then, while I was pulling the trolley to restock the cafes with boot scrapers, some of the department chaps stopped for a chat, and one of them noticed that a tyre was splitting! It survived the trip to the Flag & Whistle, but then I had to replace the tyre. Fortunately, I had a spare, because when the previous tyre exploded, I bought two new ones. I suppose I better buy two more, pronto!

Alex & Chris [Dept] were cleaning 2807 during the afternoon. Chatting with Chris, he said that he had cleaned her the other week, gone for lunch, and she was covered in dust again when he returned! Something has to be done about the restoration work in the shed affecting the running locos!

Saturday’s work day is cancelled, as there is a Lego exhibition in the yard. Call us lazy, but we elect not to park in the field and walk all the way through the station and up into the yard! It’s worse at the end of the day, of course, walking back. So, we either don’t come at all, or go to Winchcombe.

2807 is rostered to be in service on 12th, 13th, then 15th to 20th inclusive. She will then have a boiler wash-out and a rest.

As there is not a lot of excitement with 2807 (fortunately), here are a couple of photos from today showing some other motive power that has arrived recently.


D2280 and 11230


Roger

Sunday, 22 April 2018

Maintenance Update (clack, gauge, fire, connector)

Wednesday 18th
Bruce tackled issue 14 (flange lubricator not contacting wheel). Paraphrasing Bruce’s comment, ‘It took less time to insert a new graphite block than it did for the driver to log this issue!’

Bruce had dug out some new top clack castings from our spares pile. They needed quite a lot of work doing on them to bring them up to spec, apparently. So, Bruce machined the parts at home and on Wednesday replaced the existing top clacks with these new ones. [Photo depicts path of water from injector up to the top clacks (red arrow)]


John G got stuck into boot scraper work. He noticed that the F&W had none left to sell, so re-stocked them with three more.

Gil climbed into the waterproof gear and cleaned some of the underneath of the loco. Bearing in mind the ambient temperature (~25°C) that was brave of him! Thereafter, he played with the hydrostatic lubricator. There was a problem with a rubber seal and also the regulator tap needed re-packing.

A Loco Dept chap cleaned the running boards during the morning, but then had to do it again after lunch … this is a problem of the shed being both a running shed and a restoration shed, methinks!

Saturday 21st
David tackled issue 15. He changed the glass and rubbers in the gauge frame, and replaced the Klinger seal in the drain tap. It appears that there are two types of Klinger sleeve - one with oval eyelets and one with round eyelets. Some of the eyelets are loose, and David thinks one was actually missing from the sleeve in our gauge frame drain tap.

David later adjusted the ejector handle to make it vertical when in the “off” position. It is normal practice to have handles vertically aligned when “off” (apart from said gauge frame drain tap!). However, they are mostly on taper shanks and after having a few hefty bashes by the crew, tend to slip round a little.

Finally, David cleaned the running board yet again! [Photo: just look at the crap that settled on our loco today!]


Bruce was measuring the blow-down valve pipe. We plan to fit a ‘standard’ fire-hose connector to make it an easy and speedy method of filling the boiler. Needless to say, the pipe and the hose connector have different diameters! The pipe is quite low to the ground, too, because it would normally discharge steam into a pit. So, the pipe will need shortening.

Blow-down valve pipe
fire-hose connector
diagram of fixing hose connector to pipe

Bruce, John T, Rob and I turned to boot scraper production, because the cafes had sold 7 during the week, so we need to build up stocks once again. Bruce was on painting; John angle-grinding, wirebrushing and bolt cutting; Rob manned the needlegun; and I was painting the lettering and fitting brushes. The production line had 9 black bottoms; 4 primed tops, plus 6 finished articles. P-Way delivered us a pile more rail chairs, fortunately.


All issues are now resolved apart from the pin-hole in the injector steam pipe, which we shall tackle in due course. It is not a serious leak, and the pipe is “fun” to remove, and even more fun to align the top & bottom pieces either side of the leaking sleeve!

Sunday: F&W sold 4 more boot scrapers! I popped down to restock both cafes (once again). I also applied a top coat to the four that Bruce primed on Saturday.


Roger

Saturday, 14 April 2018

Maintenance Update (token, frost, graphite, frame)

Tuesday 10th
I felt the urge to go to Todders and stock up both cafés with boot scrapers. It just happened that 2807 passed by …



Note that token exchange is the fireman’s most fun task. (S)he has to hand over the token for the section just traversed and simultaneously collect the token for the section ahead … without dropping either! Dropping that which you are handing in is mildly embarrassing, but the signalman will only mutter under his breath. Dropping the one you are supposed to have collected is grossly embarrassing, because the driver has to stop the train while you walk back and find it!

Wednesday 11th
With 2807 in service, there was only one thing to do … and it was not warm! Frost crept over my needle gun, Bruce was smartening up chairs with the angle grinder and wire brush, while John G was painting in the warm!


Six black bottoms & five green tops completed.

Saturday 14th
Loco roster is all changed (again); 2807 now in service: April 14th & 15th; 23rd to 26th, 28th & 29th.

Bruce, John T and I pressed on with boot scraper production (the F&W had sold 3). Fred & Gil popped in for lunch then buzzed off again! They had been doing some painting on the siphon van.

Only two new issues raised during the week (both by Driver IB on 8th):

14: Driver’s side flange lubricator loose / no contact with flange.
{This is probably that the graphite block has worn out and needs a new one inserting}

15: Gauge frame intermittent leak from bottom nut.
{Normally this is cured by tightening the nut a little bit! It compresses a rubber seal.}

2807 should be having a rest now until wartime weekend, so Bruce may be able to get on with replacing the clack valves. We want to fit a standard fire hose connector to the blow-down valve for faster filling of the boiler (when cold!). Also the leaking injector pipe could do with mending.


Roger

Saturday, 7 April 2018

Maintenance Update (brakes, rail, seats, faces)

Wednesday 4th
Bruce had barely arrived before he was asked to release the brakes on 2807 because they wanted to move it (and couldn’t!). Apparently, the piston in the vacuum cylinder had stuck up at the top, holding the loco brakes on! Bruce found a suitable length of wood; wedged it above the actuating bar and heaved the piston back down. Once started, it dropped easily.

The loco was then hauled out and the ashpan was cleaned by Loco dept chaps. We needed her over a pit, anyway, to tackle the jobs on the issues list:

5 pep pipe leaking - Bruce had fixed this last Wednesday, but not signed-off. So that was easy.

6 Driver side, under cab side, main steam pipe to injector leaking at joint/sleeve. Can’t fix it until the loco is not required, or on standby, because of having to remove the pipe, re-braze the sleeve, and fit it back together. This might be more than a one-day job.

8 Gauge frame drain-down tap out of line (vertical) when closed. Bruce & Gil tested this, but it seems OK now. It is possible that Mark Y fixed it. It required a new Klinger sleeve within the tap, and Mark had said that he had some and that he also has a gadget for fitting them.

10 Both clack valves passing-by steam. Bruce’s homework was to play with a new pair that we had in our spares pile. He measured then against the drawing and adjusted them for clearances. He also made a groove in the surface, which seems to give a better seal. All that remains is a hole to be drilled for the fitting of a c-spanner. Then he can replace the clack valves.

11 Fireman’s side flange lubricator spring broken. New coil spring required. JC supplied a new coil spring and Bruce fitted it. Arrows point to the graphite lubricator rubbing on the wheel flange and the other end where the spring goes in.


12 Loco brakes now require adjustment. Gilbert and Nigel [Loco Dept] were left to adjust the loco brakes. There’s a “bottle screw” with a “left-hand” thread on one end, and a proper thread on the other. By turning the “bottle” it lengthens/shortens the brake rods. That’s Nigel wielding the King Dick.


13 Tender brakes now require adjustment. More than 8 turns on handbrake. Bruce examined the brake handle and found that it only requires 6 turns to apply the brakes. A second opinion was sought, and the result was that the tender brakes are declared fine! Issue rejected.

Since folks were busily fixing problems, and the cafés have been selling boot scrapers like mad over Easter, John G and I dodged the showers to progress some of the chairs in the production line.

Saturday 7th
2807 was in service, so nothing to do but boot scrapers!

Well, apart from Stefan coming to collect the rail, chairs, keys, nuts & bolts that he has acquired from the P-Way Dept for his back garden! Luckily, Stefan had been able to borrow a flat-bed truck, because it is a three-man job lifting each rail. Today, we had Brian and Dixie join Bruce, John T, Gil and myself here, so we easily loaded Stefan’s truck. Except, where was Gil? Gone for a ride!


While waiting for Stefan to arrive, Bruce had spotted that the bottom hinge of the gate leading into the yard had been “modified”, causing the gates not to close properly. Here he is removing the four bolts that hold the hinge to the sleepers. That’s Dixie, John, Brian, and Bruce in the orange with the spanner. 😊 Bruce took it away, prep’ed it and got it welded back together.


Bruce brought his homework in for marking. He has prepared the clack valves, their seats and faces. Note the groove which experience has shown improves the seal. There is also a small hole (almost not visible) into which a c-spanner can be hooked to tighten the pieces.


The weather was not a wet as the Met Office had promised, so boot scraper work commenced! Dixie was painting rail chairs. By end of play, there were six black bottoms plus three green tops.

John was cutting off bolts, angle-grinding off rough edges and wire-brushing chairs during the morning, and then moved on to needle-gunning more chairs during the afternoon.

Bruce joined in, angle-grinding and wire-brushing during the afternoon.

I started the morning with needle-gunning, moving on to fitting brushes and painting after lunch. Four BR(W) / GWR boot scrapers completed plus four LMS / BR top-coated.

Hang on, where was Brian? Gone for a ride!

Typical! Here’s John beavering away with the needle gun, and where is everyone else? Standing looking at the engine!




Roger

Tuesday, 3 April 2018

Maintenance Update (polishing, connecting, outstanding, Broadway)

Wednesday 27th
Alex and her happy band had already cleaned much of the loco, but there was still some brass and copper than could do with a shine. The trouble was, we had been moved out of the shed into the rain for work to be carried out on the shed lighting! Furthermore, they were pouring concrete all morning just by the track that we were on, which stopped us from moving. Eventually, we were shunted back inside and work began.

Fred started by wiping the rain water off the boiler top so that he could sit up there and polish the brass bonnet.



John G, Bruce and Gilbert all crammed into the cab.

John started around the gauges, polishing everything that would shine. Having moved across the cab, he finally attacked the condensing coil in the cab roof, which appeared to have been painted. If it was paint, it had flaked off (due to the heat, of course) and looked a right mess! So, that had the John-G treatment, too.


Gil fitted extra packing into all five of the sight glass taps on the hydrostatic lubricator. This had been making a mess with its oil, which might have been leaks or it might have been duff glass (too thick walled). In due course, Gil became gopher for Bruce.


Initially, however, Bruce tackled the pep pipe tap that had been dribbling. He lapped that in. Once that was done, he moved on to the next issue - oil feed pipes loose. People had tried tightening their nuts, but to no avail, so Bruce had them off and inserted some copper wire as packing.


Being stuck between the frames beneath the boiler, it is at this point that it is quite handy having a gopher on the outside!


John G ended up finishing the cleaning of the connecting rods.


John T and I were on boot scraper production (in high hopes of flogging a few over Easter). John wire-brushed and angle-ground a couple and then slapped black paint on the bottoms of five.

I attempted to needle-gun one, but there wasn’t enough time between showers to finish it! Rain + rust = brown soup.

Being concerned about the top clack (waterfeed) valves passing steam by, Bruce and Gil went in  search of spares in our pile of pieces. Two were found, and Bruce has taken them home to examine and determine if it is more sensible to replace ours rather than lap them in yet again. He has an idea that the gap within the valve gets larger the more you lap them in and it might by now exceed the specification. That might explain why they don’t last long before passing steam again.

Saturday 31st
Awful weather plus loco in service meant that there was no point in coming to Todders. However, I did paint primer onto eight rail chairs. Gilbert was on PR duty at our stand in Winchcombe.

2807 performed almost faultlessly (well, you can argue that she performed faultlessly, it’s just that things wore out! Issues logged to date and outstanding are:

5 pep pipe leaking - was fixed last Wednesday, but not signed-off.
6 Driver side, under cab side, main steam pipe to injector leaking at joint/sleeve.
8 Gauge frame drain-down tap out of line (vertical) when closed.
10 Both clack valves passing-by steam.
11 Fireman’s side flange lubricator spring broken. New coil spring required.
12 Loco brakes now require adjustment.
13 Tender brakes now require adjustment

For those of you who would like to see 2807 in action, she is currently rostered for 19 to 26 inclusive, plus 28 & 29.

Friday 30th
At 13.03 (three minutes early) 2807 approaches Broadway for the very first time … and the heavens opened up! Fortunately, the weather had managed to stay dry for the morning, but BBC weather said it would rain at 1 o’clock … and it did!


Timeline Photos posted the following on Facebook, of 2807 as she arrived for this first visit.


See also https://www.youtube.com/watch?v=g2jNjm7_pmw
(2807 appears at 4min 40secs).


(The content of external web sites linked to from this blog is not the responsibility of CSP Ltd)

Roger

Sunday, 25 March 2018

Maintenance Update (vacuum, plug, Hall, niggles)

Tuesday 20th
Warming fire required in readiness for a test run on Wednesday.

Wednesday 21st
I’m not sure who lit the steam-raising fire this morning - it could have been Jamie, Chris-1, Chris-2 or even John H. Anyway, there was 60 psi on the clock when I arrived at 10.30. Bruce and Gil were going round all of the oiling-up points. As the loco had been stood idle for months, all of the pots were empty. Hence it took all morning to complete this task.


Note that it takes three people to oil the vacuum pump - one to hold the oil can; one to tip it up, and one to manage the process. 😉

Then disaster!

Plug no.18 was leaking. As pressure rose to 130 psi, there was a major plume emitting from the lower part of the plug. John H declared it a failure, and immediately began to deaden the fire to prevent pressure rising any more.


I find this extremely odd, as 2807 passed her steam test on 2nd March; Mark Y nipped up plugs that were wisping steam on 6th; and today this one is gushing steam dangerously. Has someone removed it and not fitted it back tightly while we were not looking, or what?

While there was pressure, JC ran her up & down a bit to check that there were no complaints from bearings, valves or cylinders. This all went very well - no problems at all.

The problem then was how to get pressure back down! 2807 is well known for holding the heat - maybe she has an efficient firebox/boiler. So, injecting (cold) water helped a little; opening the steam heating and venting it helped … a little; eventually a blow-down had to be undertaken to make room for more water in the boiler! By 4 pm, pressure was down at 15 psi.


Mark came in and replace plug 18 with a new one on Thursday. The hole’s thread needed re-cutting.

There were a few niggles that turned up. The slacking pipe (aka “pep” pipe) dribbles constantly. There was a drip from the condensing coil in the cab roof. The drain cock on the gauge frame doesn’t line up correctly. One of the glasses in the hydrostatic lubricator totally clogged up with oil.

The cock on the pep pipe is going to be replaced with an improved design within a few weeks, so we can ignore that.


Bruce fixed the condensing coil.

Bruce also sucked the oil out of the glass and cleaned that.

John G was here today, too, but it was difficult to know what to do, since it was “all go” and then “all stop!” However, he applied some elbow grease to the coupling rods, cleaning off some rust spots and places where paint had crept round from their backsides.

Apart from playing fireman for a while, I just needle-gunned four chairs.

Saturday 24th
Alex lit a warming fire on Friday, and Ade + Eleanor were crew today. Alex and Gwendolyn did a spot of cleaning (inside the cab had been in an awful state). The glasses on the hydrostatic lubricator kept oiling-up. JC replaced them - apparently some new glasses were not quite to spec.

In due course, steam was raised; the plug behaved, so she went for trip double-heading Foremarke Hall. Gil went along for the ride.


There were a couple of niggles (as usual) - she wouldn’t raise enough vacuum in the reservoir (so Foremarke helped). Bruce tightened the gland on the loco vacuum cylinder, so hopefully that will be OK now. The new rod bearings are working fine - not over-heating or anything.




Here she is heading back into Toddington (Foremarke is at the rear). Ade commented that he hardly needed any more regulator than usual even though there was an extra 125 tons at the back!


Apart from the loco, John T, Rob and I prepared some railwayana for a customer who is building a section of railway in his garden. Rob did a spot of welding, including some for Dinmore Manor. Then we turn our attention to boot scraper production, ending the day with four black bottoms, four angle-ground and one waiting its turn.

Issues logged and outstanding are:
5 Pep pipe leaking, Valve needs seating. {We’re awaiting a new type of valve}
6 Driver side, under cab side, main steam pipe to injector leaking at joint/sleeve.
8 Gauge frame drain-down tap out of line (vertical) when closed.
9 Oil feed pipe to crown on right hand side driver loose. Unable to tighten nut further.
Ditto driver’s side intermediate.
10 Both clack valves passing-by steam.

For those of you who would like to see 2807 in action, she is currently rostered for:
Train 3 on March 30 & 31
April 1 & 2; and then from 19 to 26 inclusive, plus 28 & 29.


Roger

Saturday, 17 March 2018

Maintenance Update (Manor, Grange, height, felt)

Erratum
Several people corrected my assertion last time that No.1 boilers are used on Manor class. They are not, of course. I should have said Grange class. Manors had smaller (no.14) boilers and were not fitted with large ejectors (as far as I am aware) possibly because they were used on secondary lines where traffic was not heavy and the extra “suck” therefore not deemed necessary?

Here’s the large ejector on Foremarke Hall: back half, and front half leading into the smokebox.



Wednesday 14th
Part of the mechanism that operates the drain cocks is held together with a tapered pin. JP reported that the pin is too far into its hole and needs replacing with a longer pin. Gil started on this; removed the old pin and tried to fit a new pin. However, not only was the new pin too long, but it took Bruce to get it back out again. We could not find a suitable tapered pin, so the old one has gone back in for now. {Just look at the filth!}


The hydrostatic lubricator drain pipe in the cab had been rubbing against a floor panel. John G modified the panel and repainted it. Then he made a couple of rubber garters to fit round the pipes to reduce the risk of wear.


John then refitted various ferrules around washout plugs, and Gil found one to fit, too.

Gil oiled the front valve spindles to be sure they are lubricated before the loco moves very far.

Bruce also tackled oiling-up. He started by checking the felts that lubricate the piston rods. These looked good.


Checking the oil in the pots revealed them to be full of water! So, he sucked the water out and refilled the oil pots.


We requested a steam test before being put into service, to check all of the seals and joints are steam-tight. This is currently planned for next Wednesday.

Friday 16th
MY reported to us: “I have heard the loco is sitting at a funny angle, very low on back corner and
high on the opposing front corner. This may simply be the loco is "stuck" from the jacking up that
took place last weekend …”

I was gardening at my daughter’s until 11.00, when I decided to pack up & go home … it’s “The
Races”, isn’t it?! Winchcombe: gridlocked. I could not turn into Castle Street (it’s only wide enough for one car, and there was a queue waiting to come out of it!) So, I thought: ‘Where else can I get a cuppa? Ah-hah! The railway!’ So I managed to turn round and head for Todders, thinking that I’d measure the loco heights while there. When I arrived, our container door was open! Who’s doing what, I thought? It was Rob. He was cleaner on Dinmore, and while waiting for it to come back from Cheltenham, he was cleaning 2807 instead. We measured the height of the running boards, and sure enough, the front is 2” higher on the right-hand side, and at the cab end it is 1” higher. But we had jacked her up on the RHS and let her down slowly. I hope it is just that she’s a bit stuck.

Saturday 17th
It was a tad cool today (viz. icicle on tap).


I began by doing a little gardening, filling in a couple of gaps with alliums and bluebells. Our garden is coming along nicely - various spring bulbs popping up. But, by heck, my fingers froze!


We decided to take a look at this dipping of the frames. Gil & I jacked up the LHS and then let it down. That had some effect, but not a lot. Later in the day, Jeff [Loco Dept] wanted to pull Dinmore and Foremarke out to be coaled. So, I asked him to pull 2807 out, too, and he pulled her down the track a way and then back. It did improve things a little, but (as Bruce pointed out) the front buffer beam is at an angle anyway!

In this photo, I have lined the camera up with the side running boards, and you can see that the buffer beam RHS (as you look at it) is definitely lower. One can only assume that 2807 suffered a heavy shunt at some stage of her final years in BR service.


Bruce carried on making new felt pads for lubricating the LHS piston rod. The new ones are soaking in oil during lunch.


Rob and Alex continued cleaning the rods.

Gil showed Rob where he was to grease the loco underneath.

Finally, we moved the Pecket and Dinmore’s new tender to the end of their road so that P&O has room to sleep tomorrow night.

Pushing the Pecket turned out to be no easy thing. With five of us heaving at it plus three using pinch-bars, it was a struggle to get it to move.


The tender, on the other hand, heavier though it obviously is, moved quite easily with five of us pushing, and no-one on pinch-bars!

For those of you who would like to see 2807 in action, she is rostered for:
Train 3 on March 30 & 31;
 April 1, 2; and then from 17 to 26 inclusive, 28, 29.


Roger