When 2807 was
pulled out of Woodham Brothers scrapyard in 1981 and moved to
Toddington, it was the first time that people on the team had
achieved such a thing. When the loco was re-wheeled in 1996, it was
the first time that people on the team had achieved such a thing. I
think you can see where this is going. A similar story when 2807
re-entered service in 2010. And now we commence the next phase, the
first heavy general overhaul - and we haven't done this before
either.
We're not
particularly concerned about this (did somebody say “famous last
words”?) because as a team we've built up considerable expertise
over the years, and we're surrounded by people who have done this
before and will give us advice when we need it. And not having done
something before didn't stop us achieving the previous milestones, so
let's do it again.
I'm pleased to say
we have a plan. I kept hold of the plan when we completed the
restoration (I was project manager then). So it's been updated to
reflect an overhaul rather than a restoration, and Gilbert has split
the work between teams so that things should be happening
concurrently once we get going. I say once we get going, but by the
time you read this it will have started. The last two operating days
for 2807 were 31st
December and 1st
January. Withdrawal followed on 2nd
January and work started the same day.
In fact some things had already started. Last winter we completed
some work on the valves and cylinders. That was originally planned
to be overhaul work, but an opportunity arose to carry out the work
early, so we took it. And, during 2019, we contracted Ian Carpenter
to build us a new ash pan, ready for when the boiler overhaul work is
completed.
I'm sure you're aware that the biggest piece of work to be completed is usually the boiler. It's usually the biggest piece of work because certain things have to be done each overhaul (new tubes for example), and there may be a lot of other work to do. We won't know how much other work is necessary until the boiler can be examined and tested. The other reason it's the biggest piece of work is because it requires suitably qualified people to work on it, which means the volunteers can't do it. And this means it's going to be expensive. What we do know though is that, following a tendering process, Riley and Son (E) Ltd of Heywood, Lancashire will be completing the work. It is anticipated that the boiler will be transported to Heywood mid-2020.
Which brings me on
to financing the overhaul. There are certain things that have to be
done, and some of these have to be contracted out (the boiler for
example). Other things have to be done, but the volunteer team could
do them. There are likely to be more things that we discover during
the work, and which have to be done, either contracted out or by the
volunteers. And there are still more things that strictly speaking
don't have to be done, but while the loco is in pieces it makes sense
to do them rather than store up problems for later on.
We believe that we
have the finance for the things that we know about and which must be
done, and also the things that it makes sense to do at the same time.
But additional finance will assist in two scenarios. One is that we
discover significant additional work that needs doing. The other is
that we wish to shorten the duration of the overhaul by contracting
out more of the work.
It's worth
mentioning here that our main source of income is steaming fees.
During the overhaul there's no steaming, and so no fees. If the
money runs out then the overhaul will stop until sufficient funds can
be raised (by other means) to complete the work. What we need is a
steady flow of income other than steaming fees. We already have a
very loyal group of supporters who always come up trumps when we need
them. If you would like to join this group, then please take a look
at the pages on this web site where
you will find information about ways to help, and the benefits that
brings.
Steve